Toggle navigation
Home
People
Theses
Tracker
TileCal
Trigger
Midwest Tier2 Center
Physics
Links
Join Us
HEP
Tile Calorimeter
Tile Calorimeter Phase I
Go to Phase II documentation
Upgrade
Mechanical Details
PMT Block
Motherboard for LV & Control Signals
HV Control & Distribution in the Drawer
Digitizer System
Readout Driver
Level 1 Trigger
Interface Board
External LV Supplies
Notes and Writeups
Software for 13bit Version of 3in1 Cards
Radiation Testing
Design Review
Production Readiness Review
Submodule Construction
Commissioning
Trigger Signals
Other Sites with TileCal Info
Schedule and Quantity (Motherboards)
Motherboard procurement plan
Institute in charge
University of Chicago
Person in charge
Jim Pilcher
Quantity
270 finished sets of 4 cards each (including 5% spares)
Production schedule
pre-production batch in 99
start: 1-7-99, end: 1-9-99
final production batch in 99
start 1-11-99, end 1-1-00
burn-in and testing
start: 1-12-99, end: 1-4-01
Distribution to
Clermont-Ferrand (drawer assembly site)