Progress on rework of TTC Mezzanine Cards |
|
23-Jul-03 |
|
|
|
|
|
|
|
|
Number |
Date |
|
|
Card sent to Promex for quote on rework |
1 |
|
|
|
Sample returned from Promex |
1 |
9-Dec-02 |
|
|
Richard sends first batch from CERN |
103 |
9-Dec-02 |
|
|
Cards sent to Promex from Chicago |
103 |
16-Dec-02 |
|
|
First article of production received from Proxmex for review |
1 |
8-Jan-03 |
|
|
Balance of cards received from Promex |
102 |
15-Jan-03 |
|
|
First shipment of reworked cards to CERN |
50 |
17-Jan-03 |
|
|
Second shipment of reworked cards to CERN |
40 |
27-Jan-03 |
|
|
5 MB1 sections shipped with reworked Mezz. Cds. |
5 |
31-Jan-03 |
|
|
Richard sends second batch from CERN |
136[1] |
5-Feb-03 |
|
|
2nd batch of cards sent to Promex from Chicago |
163 |
14-Feb-03 |
|
|
2nd batch of cards sent from Chicago to CERN |
155 |
15-Mar-03 |
28-Mar-03 |
|
9 MB sets sent, including reworked Mezz. Cards |
9 |
8-May-03 |
|
|
7 reworked Mezz. Cds. Shipped to CERN from Chicago |
7 |
11-Jul-03 |
|
|
|
|
|
|
|
|
Totals |
|
|
|
|
|
|
|
|
Need |
|
|
|
|
Reworked |
Rework |
Total |
|
At CERN/Stockholm/Clermont |
266 |
10 |
276 |
|
|
In modules in Bldg. 175 |
|
5 |
|
|
|
In Bldg. 40 (available for shipment) |
|
5[2] |
|
|
|
Shipped to CERN 17 and 27-Jan-03 |
90 |
|
|
|
|
Shipped with MBs on 3-Feb-03 |
5 |
|
|
|
|
Shipped to CERN 15-Mar-03 |
155 |
|
|
|
|
Shipped to CERN with MBs on 8-May-03 |
9 |
|
|
|
|
Shipped to CERN on 11-Jul-03 |
7 |
|
|
|
|
|
|
|
|
|
At Chicago |
1[3] |
|
1 |
|
At Promex |
0 |
0 |
0 |
|
|
|
|
|
|
|
TOTAL |
|
267 |
10 |
277 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Mezzanine cards built (272+8) |
280 |
|
|
|
Received from Promex after rework |
|
|
|
|
|
Batch 1 |
104 |
|
|
|
|
Batch 2 |
163 |
|
|
|
|
Batch 3 |
|
|
|
|