Pulsar and mezzanine cards prototype, production test plan and schedule
Pulsar and Mezzanine cards prototype and production test plan
Pulsar project schedule
- April 2002: Finish Pulsar board schematics work, continue layout and board level simulation, continue firmware development;
have core firmware ready for simulation with mezzanine cards by early May;
- May 2002: Finish first round Pulsar board level simulation work, finalize the schematics; finish hotlink mezzanine cards (Tx/Rx) prototype testing
without Pulsar motherboard;
- June 2002: finish board level simulation and mutli-board level simulation to validate
the design... simulation will continue after that as well. finish layout. Pulsar Review(?).
- July. 2002: release Pulsar prototype.... have Pulsar core firmware for teststand ready.
start Taxi mezzanine card and AUX card design. start prototype testing software work.
- Aug.-Oct. 2002: testing Pulsar prototype with SLINK test tools and hotlink mezzanine cards;
decide if there will be Rev B for Pulsar or not.
start hotlink mezzanine cards production if succesful; send out Taxi version mezzanine cards and AUX card;
- ? 2002: if Pulsar prototype testing is sucessful, Pulsar board and hotlink mezzanine cards
(and firmware) should be ready for commissioning as Level 2 teststand at B0.... depends on manpower!!