Progress to Date
We are in the process of collecting the necessary materials.
10/22/98 -- Received 26 pallets of
master plates
10/23/98 -- Received 13 pallets of
master plates
10/28/98 -- Received 26 pallets of
master plates
11/24/98 -- received
Timesavers machine
11/24/98 -- received
stacking fixture
1/10/99 -- expect to receive
glue
2/??/99 -- received head for
gluing machine
4/14/99 -- received
spacer plates
4/27/99 -- received
weld_bars
4/29/99 -- expect to finish construction of
gluing machine